TII partners with Pinergy to deliver significant rooftop solar installations at Luas tram depots

  • New rooftop solar installations at Broombridge and Sandyford Luas Depots expected to offset more than 11% of the depots’ combined electricity consumption
  • TII plans a third rooftop solar installation at the Red Cow Luas depot in 2027

Transport Infrastructure Ireland (TII) has completed major rooftop solar PV installations at its Broombridge and Sandyford Luas tram depots in Dublin, enabling the facilities to generate on-site renewable electricity from their own rooftops.

The total annual electrical consumption of the two depots combined is 4,150 MWh of which the photo voltaic system that was installed by Pinergy offsets more than 11% of the combined depot electricity consumption.

The installation across both depots comprises 1,181 solar panels, with a combined system DC size of 530 KWp covering an area of approximately 2,359.8 m² of depot roof space with a carbon emissions saving of 149.7 tonnes annually.*

Electricity generated by the systems will directly power daytime operations at the depots, which include administrative offices, tram maintenance facilities, wash plants and sanding plants. Any excess renewable electricity generated will feed into the Luas overhead DC power system, supplying renewable electricity for tram services.

TII has designated its three Luas depots as Significant Energy Users and together they account for 27% of total electricity consumption across the network. The solar installations will therefore contribute to reducing the carbon footprint associated with operating and maintaining Luas services.

Luas carried 55 million passengers in 2025, underlining the scale of the public transport network that TII is seeking to progressively decarbonise. TII is planning a third solar installation at the Red Cow depot in 2027 as part of phase two of the rooftop solar PV array programme.

John Connolly, Senior Engineer Energy and Systems at TII said: “Generating renewable electricity at our Luas tram depots is a practical step towards reducing the carbon footprint of operating and maintaining the network. These facilities are significant energy users, so using their large roof areas to generate clean electricity makes both environmental and operational sense.

“The project will contribute to the objectives set out in TII’s Climate Action Roadmap and support the Government’s target for the public sector to reduce greenhouse gas emissions by 51% by 2030 under the Climate Action Plan.

“Delivering the installations within live depots required careful coordination between TII, Egis, TII’s Luas operator and Pinergy. The work was completed without disrupting tram schedules, maintenance activities or day-to-day depot operations. That experience provides us with a proven model as we prepare for the next phase at Red Cow depot.” 

Philip Connor, Head of Commercial Development at Pinergy, said: “Installing solar within a live public transport network was a complex undertaking. The challenge was to design and install the systems around continuous tram movements, live infrastructure and essential maintenance schedules, without affecting Luas services.

“Broombridge and Sandyford Luas tram depots demonstrate how large public infrastructure assets can become renewable energy generators in their own right, playing a key role in the energy transition for the transport sector.”

This latest project offers a strong model for similar installations across Ireland’s wider transport estate, including bus depots, rail stations, park-and-ride facilities, and freight and logistics hubs.

*Which is equivalent to the amount of carbon dioxide absorbed by approximately 10,962 trees in one year.